For repeat production of small metal parts with complex shapes, review stainless steel or titanium feedstock, sintering shrinkage and critical post-machining features with the drawing.
As-sintered tolerance for initial review
±0.3%–±0.5%
Wall thickness for initial review
0.5–6.0 mm
Tooling and T1 planning estimate
25–35 days
Confirm by drawing and trial samples. Timing starts after tooling release and schedule confirmation.
MIM-316L: confirm fork symmetry, spring-bar hole alignment and gate location away from the visible face. Agree a mating gauge and a finish sample for mirror polish or PVD.
Loaded lever and miniature gear
MIM-17-4PH: confirm tool release, profile or tooth geometry, and hardness and fit after the specified aging treatment.
Lightweight titanium structure
Ti-6Al-4V: check thin-wall distortion and ceramic support, and agree chemical, density and mechanical testing at trial stage.
Metallography, dimensional inspection and protective packing
Sectional porosity and immersion density
Embed and polish the agreed section for microscopy. Record location, field count and area fraction separately from bulk density by immersion. Set furnace-lot sampling during trial approval.
CMM, optical measurements and first article inspection
Select CMM, optical measurement or a gauge according to access and datum. Record cavity IDs and measurement condition. Agree sampling and any Cpk target on named characteristics.
Compartment trays and feature protection
Separate polished faces and protect threads where needed. Specify tray material, ESD properties if required, and the label linking each package to its production lot.
From drawing review to batch release
Drawing review and DFM
Review the STEP model and 2D drawing, grade, annual demand and secondary operations. Agree the quotation scope and the trial plan.
Tooling and T1 trial
Build the mold and setters for the selected feedstock, then mold and sinter the T1 samples to verify the initial shrinkage compensation.
25–35 days · Tooling and T1 planning estimate
First article and metallurgy
Check cavity-by-cavity dimensions and fit. Submit agreed density, porosity and mechanical test results before approval.
Production lot release
Freeze the approved process revision, complete secondary work and dispatch with the agreed packing and inspection records.
Frequently asked questions
When should MIM be evaluated first?
Start with small, complex parts whose design is stable and whose recurring demand can cover mold and qualification costs. CNC prototypes can verify fit before tooling.
What information is needed before tooling?
Send the STEP model, 2D drawing with datums, target alloy and condition, annual and batch volumes, cosmetic zones, critical fits and inspection requests.
Does immersion density prove ≤0.5% metallographic porosity?
The two tests measure different properties. Specify both criteria separately, including the section locations and image analysis method for porosity.
How do I choose between 316L and 17-4PH?
Evaluate 316L for corrosion-sensitive parts. Evaluate aged 17-4PH when strength or hardness drives the decision. Agree the delivery condition and acceptance tests for the chosen grade.
Can titanium MIM be trialed in a small lot?
Trial feasibility depends on feedstock, minimum run size, wall geometry and the required oxygen, nitrogen and mechanical checks. Agree the sample and test plan before release.
Can gate, parting-line or ejector marks be removed?
First locate them away from cosmetic and sealing areas wherever feasible. Assess trimming, machining or polishing and approve limits with a sample.
Send drawings for engineering review
Send drawings and quantities with the selected route, alloy and finishing requirements for review.
Engineering review brief
Choose a process focus and describe the critical requirements. Your choices will be included in the enquiry.